Kaptur – six months into the project (1/3)
Posted: April 10, 2012 Filed under: monthly reports, project posts | Tags: CARDIO, DAF, Digital Conversations, DMP Online, environmental assessment, funders, implementation plan, jiscmrd, modelling, RDM policies, Research Councils, technical analysis, The British Library Leave a comment »One third of the way through the project, and this is our update for the end of the sixth month:
WP1: Project Management
- the second steering group meeting has been arranged for July in London (before the Olympics!)
- the implementation plan is available as a blog post
WP3: Technical Infrastructure
- The Technical Analysis report has been through several iterations; the user requirement component has been sent to the partner institutions for final feedback; once this is received the requirements testing will take place leading to the choice of technical system for the pilot.
WP4: Modelling
- The Project Officers reported on the trends in funding at their institutions (blog post)
- Three of the four Project Officers attended the JISCMRD two-day workshop on institutional RDM policies (12-13th March, Leeds); this was extremely beneficial for Kaptur for several reasons:
- using the Chatham House Rule the JISCMRD projects could talk openly and plainly about the reality of creating and seeking approval for institutional RDM policies
- we had an opportunity to really understand the processes and workflows from more experienced projects (i.e. those who had received funding in the previous JISCMRD round 2009-11 or who already had institutional RDM policies)
- it was very interesting to hear how other JISCMRD projects were making use of the CARDIO and DAF tools from the Digital Curation Centre – we will be discussing this at our next project team meeting in April
- there was also the opportunity to ask questions of select representatives of the Research Councils UK (RCUK) which was very illuminating, particularly in terms of the EPSRC Expectations
- as most of the project team were able to attend we could discuss and share our own views over the course of the two days and come to a consensus of opinion – i.e. that we were aiming for a high-level aspirational policy based on University of Edinburgh’s policy
- An RDM Discussion paper was drafted and was an agenda item at the UCA Research and Enterprise Committee meeting on 30th March; this Committee also have the role to approve an institutional RDM policy.
- Representatives from 2 of the partner institutions attended the JISCMRD Data Management Planning (DMP) end of project event (23rd March) – this was useful in terms of discussion throughout the day, lessons learned from other projects, and also take-home resources which we may be able to implement – as well as a sneak peek at the new and improved version of the DCC’s DMP Online tool due to launch soon.
WP7: Dissemination
- As mentioned above, 3/4 institutions attended the JISCMRD policies workshop and 2/4 attended the DMP end of project workshop (both March 2012).
- Promotion of the Environmental Assessment report (blog post)
- Beginning of an idea for more creative publicity material for Kaptur, to be followed up at our next project team meeting
- The Project Manager gave a presentation on Kaptur to British Library staff as part of their Digital Conversations event (blog post)
- The Project Director and Project Manager co-authored a written paper on Kaptur for the EVA London 2012 conference
4. Issues/challenges
As we are now a third of the way through the project it is a good point for reflection on both the work already accomplished as well as the work still to be done. Our focus continues to be on producing a pilot model for the visual arts sector and drawing on the strength of the collaboration across four partner institutions. Added to this is a growing sense of community across the JISCMRD programme (2011-13) which has benefited the Kaptur project team.