Kaptur – three months into the project (1/6)

One sixth of the way through Kaptur, and this is our update for the third month:

1. Project Outputs

  • consortium agreement – in process of being signed (delays due to Christmas, this is now expected before the end of January)

2. Environmental Assessment

  • The 16 one-hour recorded interviews have now been transcribed. Each Project Officer has been reviewing the transcripts, marking them up and checking that they are anonymised in order to collaboratively analyse on Monday 9th and Tuesday 10th January 2012.

3. Dissemination

4. Issues/challenges

December is always a challenging month (due to leave and tying up loose ends) which is why we pressed ahead with the project work so quickly during October and November. During December we continued to build links with other projects, the DCC, and internationally at the IDCC conference. The biggest issue was making sure everything was in place for the data analysis to occur in early January including the transcripts and venue. We will be meeting at Goldsmiths, University of London and a blog post will follow here regarding our analysis.

Advertisements


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s